Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-122/2002/D Quarterly Environmental Monitoring
and Audit Report
- AUGUST to OCTOBER -
- 2013 -
|
CLIENTS: |
|
Civil
Engineering and Development Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
11 November
2013 |
2.2 Scope
of the Project and Site Description
2.3 Project Organization and Contact
Personnel
5.4. Review
of the Reasons for and the Implications of Non-compliance
5.5. Summary
of action taken in the event of and follow-up on non-compliance
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects.
lIST
OF TABLES
Table I Principal Work Activities in the
reporting period
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Contact
Details of Key Personnel
Table 2.3 Principal
Work Activities in the reporting period
Table 3.1 Continuous
Noise Monitoring Stations
Table 3.2 Air
Monitoring Stations
Table 4.1 Continuous
Noise Monitoring Stations for Contract no. HK/2012/08
Table 4.2 Air
Monitoring Station for Contract no. HK/2012/08
Table 4.3 Details of
Waste Disposal for Contract no. HK/2012/08
Table 6.1 Cumulative Statistics on
Complaints
Table 6.2 Cumulative Statistics on
Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Graphical Presentations
Appendix 4.2 Air Quality Monitoring Graphical
Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 8.1 Construction Programme of
Individual Contracts
Construction
Activities for the Reported Period
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
Table I Principal Work Activities in the reporting
period
August 2013 |
September 2013 |
October 2013 |
· Site preparation works · Site survey · Temporary works · Excavation for utilities / cooling
mains diversion · Construction of interim landing
steps · Hoarding erection |
· Site preparation works · Site survey · Temporary works · Construction of interim landing
steps · Hoarding erection |
· Site preparation works · Site survey · Temporary works · Concrete breaking · Stockpiling of fill materials |
Noise Monitoring
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-122/2002/D to implement the Environmental
Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual
of the approved Environmental Impact Assessment (EIA) Report Central Reclamation Phase III - Studies, Site Investigation, Design and
Construction (Register No.: AEIAR-040/2001) since 1 May 2013.
1.1.2. This
report documents the finding of EM&A works for
Environmental Permit (EP) no. EP-122/2002/D, during the period from 1st August 2013 to 31st
October 2013.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project Background – summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring
parameters, monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results obtained in the
reporting period.
Section 5 Compliance Audit –
summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 6 Complaints, Notification of
summons and Prosecution –
summarizes the
cumulative statistics on complaints, notification of summons and prosecution
Section 7 Cumulative Construction Impact
due to the Concurrent Projects – summarizes
the relevant cumulative construction impact due to the concurrent activities of
the concurrent Projects.
Section 8 Conclusion
2.1.1 Central
Reclamation Phase III - Studies, Site Investigation, Design and Construction
(hereafter called “the Project”) are Designated Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central Reclamation Phase III - Studies,
Site Investigation, Design and Construction (Register No. AEIAR-040/2001) has
been approved on 31 August 2001.
2.2.1.
The design and construction of Central
Reclamation Phase III involves the permanent reclamation and construction and
operation of a trunk road and its road tunnel that is shown at Figure 2.1.
2.2.2. The key
purpose of the study area encompasses the area of
·
Reclamation
and seawalls, roads and associated services, North Island Line Protection Works
and Advance Trunk Road Tunnel (ATRT) for the CWB;
·
Reprovisioning
of Star Ferry Pier, public landing steps, wallah wallah moorings, and motor
boat/launch operators' kiosks;
·
External
cooling water systems which consist of the cooling water pumping shells for
future developments, and the reprovisioning of existing cooling water pumping
stations and associated pipework systems and E&M works;
·
Reprovisioning
of existing Leisure and Cultural Services Department (LCSD)'s facilities;
·
Provision
of a flood relief path, stormwater culvert extensions, upgrading of hinterland
stormwater drainage resulting from the reclamation, demolition of the existing
waterfront structures and necessary landscaping;
·
The
Hong Kong Station Extended Overrun Tunnel (EOT) and associated ventilation
structures entrusted for construction within the CRIII works;
·
Reprovisioning
of the Government Heliport at the Wan Chai PCWA and reprovisioning of the Wan
Chai PCWA at
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the four
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated
Project |
EIAO
Reference |
DP1 |
Central-Wanchai Bypass (CWB) |
Schedule 2, Part I, A.7 |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
DP3 |
Reclamation works |
Schedule 2, Part I, C.1 |
DP4 |
The |
Schedule 2, Part I, A.7 |
2.2.4.
The designated project work I (DP1) was
awarded to China State-Leader Joint Venture HK/2012/08 as part of the Project
works by the Civil Engineering and Development Department (CEDD). The construction work under Contract no. HK/2012/08 was commenced on 27
May 2013.
2.3.1 Civil Engineering and Development Department is the overall project controllers for the Central Reclamation Phase III Project. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
|
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew TSE |
9137 1811 |
2877 1522 |
Project
Manager |
Mr. Victor WU |
9193 8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268 1918 |
|||
Site Agent |
Mr. Paul LUI |
9095 7922 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Ching Man,
CHAN |
6050 4919 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882 3939 |
2882 3331 |
2.4.1 During this reporting period, the principle work
activities of the contract is included as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai
Bypass at Wan Chai West
Table 2.3 Principal Work Activities in the reporting
period
August 2013 |
September 2013 |
October 2013 |
· Site preparation works · Site survey · Temporary works · Excavation for utilities / cooling
mains diversion · Construction of interim landing
steps · Hoarding erection |
· Site preparation works · Site survey · Temporary works · Construction of interim landing
steps · Hoarding erection |
· Site preparation works · Site survey · Temporary works · Concrete breaking · Stockpiling of fill materials |
2.4.2 Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 2.1.
NOISE Monitoring Stations
3.1.1.
The continuous noise monitoring station for the Project is listed and
shown in Table 3.1 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Continuous Noise Monitoring Stations
District |
Station |
Description |
Central |
ACL3 |
City Hall |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2. Continuous 24-hour noise monitoring shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.3. If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.4. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
3.1.5. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
3.1.6. The sound
level meter shall be checked using an acoustic calibrator generating a known
sound pressure level at a known frequency before deployment to the site and
during each site visit. Measurements will be accepted as valid only if the
calibration level from before and after the noise measurement agrees to within
1.0 dB.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure 3.1.
Appendix 3.1 shows the
established Action/Limit Levels for the monitoring works.
Table
3.2 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
ACL1 |
City
Hall |
Central |
ACL2 |
PLA Barracks |
Central |
Air Monitoring Parameters, Frequency and Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5.
High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
3.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.8.
Filter paper of size
3.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.0.1. The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing work
areas of various contracts, latest status of work commencement and monitoring
stations is shown in Figure
2.1 and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.2. In the reporting period, the concurrent
contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
4.1.1
Due to safety concerned, the location of the continuous noise monitoring
station at City Hall was finely adjusted to the roof of the City Hall, Low
Block on 1 May 2013.
4.1.2
The proposed division of noise monitoring stations is summarized in
Table 4.1 below.
Table 4.1 Continuous Noise Monitoring Stations for Contract no. HK/2012/08
Location ID |
District |
Description |
ACL3 |
Central |
City Hall |
Remarks: Continuous
noise monitoring results and graphical presentation for ACL3 during restricted
hours and night time period are for information only.
4.1.3
No exceedance was recorded at ACL3 - City Hall in this reporting period.
4.1.4
Continuous noise monitoring results measured in this reporting period
are reviewed and summarized. Details of continuous noise monitoring results and
graphical presentation can be referred to Appendix 4.1 .
4.2.1 The proposed
division of air monitoring stations are summarized in Table 4.2 below.
Table
4.2 Air Monitoring Station for
Contract no. HK/2012/08
Station |
Description |
ACL1 |
City Hall |
ACL2 |
PLA Barracks |
4.2.2 No action
or limit level exceedance was recorded at ACL1 – City Hall and ACL2 PLA
Barracks in the reporting period.
4.2.3
Due to the enforcement of Gale Signal No. 8, the 1-hr TSP monitoring at ACL1
and ACL2 on 14 August 2013 were rescheduled to 15 August 2013.
4.2.4
Due to interruption of electricity supply, the 24-hr TSP monitoring at
ACL1 on 19 August 2013 was rescheduled to 21 August 2013.
4.2.5
Due to the hoisting of No. 8 Southwest Gale or Storm Signal, the 24-hr
TSP monitoring at ACL1 and ACL2 on 23 September 2013 were rescheduled to 24
September 2013.
4.2.6
The Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.2.
4.3.1 Only
Non-inert C&D wastes were disposed in this reporting period. Details of the
waste flow table are summarized in Table 4.3.
Table 4.3 Details
of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity
this quarter |
Cumulative
Quantity-to-Date |
Disposal /
Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
288 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials disposed, m3 |
50 |
75 |
SENT
Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical waste disposed, kg |
NIL |
NIL |
NIL |
5.0.1. The Event Action Plan for construction
noise and air quality are presented in Appendix 5.1.
5.1.1
No action or limit level exceedance was
recorded at ACL3 – City Hall in this reporting period.
5.2.1
No action or limit level exceedance was
recorded at ACL1 – City Hall and ACL2 – PLA Barracks in this reporting period.
5.3.1
There was no non-compliance from the site audits in the reporting period. During
environmental site inspections conducted during the reporting period, minor
deficiencies were noted.
5.4.1
There was no non-compliance from the site audits in the reporting
period.
5.5.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
6.0.1. There was no environmental complaint
received in this reporting period.
6.0.2.
The details of cumulative complaint log
and summary of complaints are presented in Appendix
6.1.
6.0.3. No notification of summons or prosecution was received in the reporting
period. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
May 2013 – July 2013 |
0 |
August 2013 – October 2013 |
0 |
Project-to-Date |
0 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. This
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2. According
to the Monthly EM&A report (July, August and September 2013) of
Central Reclamation Phase III (CRIII) for Contract HK 12/02, surface drainage
and footpath construction adjacent to GPO, modification to the junction of Road
D8 and Road P2, modification of timber decks at advance promenade, paving and landscaping
work behind GPO boundary wall, and additional run-in at Road P2 footpath (north
bound) outside ESB S8.1 were performed in the reporting period. The water
quality monitoring was completed in October 2011 and no Project-related exceedance
was recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) undertaken by contractor HK12/02 was insignificant.
7.0.3. According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II were marine works at HKCEC areas,
cross-harbour Watermains, Fresh Watermains and Cooling Watermains
Installations, tunnel works at Wan Chai East, ELS work and
pipe roofing works at TS4 and cut and cover tunnel construction at TPCWAE, excavation
and tunnel works at Central Interchange, ELS and box culvert construction at
North Point area, bridge construction and tunnel works at Central Interchange, ELS
segment launching works and IEC parapet demolition at North Point area. The major
environmental impact was water quality impact at Causeway Bay and Wan Chai.
Land-based construction activities were diaphragm wall construction at TS2, ELS works and
excavation at TS2, ELS work and pipe roofing works at TS4, cut
and cover tunnel construction at TPCWAE, tunnel
works at Central and ELS work at North Point and tunnel works at Wan Chai East
in the reporting period.
7.0.4. The major
environmental impacts generated from tunnel works at Central and tunnel works
at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were undertaken in the
reporting period. No significant air impact from construction activities was
anticipated in the reporting period. Besides, no project-related exceedances were
recorded during the air and noise environmental monitoring events in the
reporting period. Thus, it is evaluated that the cumulative construction impact
from the concurrent projects including Wan Chai Development Phase II was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliances were noted and no
prosecutions were received during the reporting period.
8.0.3. The construction programmes of individual contracts are provided in Appendix 8.1.